Siding complete

DTE finally made it out to hook up the new house. This week the siding was completed, as well as the underground plumbing, and the drywall was hung. The basement floor was scheduled to be poured either late this week or early next. Next up: finishing the drywall!


Sunday, February 8, 2009

All Bricked!

The brick is complete - siding should be early this week!

...some pics from yesterday

Friday, February 6, 2009

Bricking this week

This week they are bricking the house and the insulation is going in. Here's an in progress shot.